Client Profile
A CPA firm contacted McGuire Sponsel to conduct a retroactive cost segregation study for their client, a metal products manufacturer specializing in stainless steel electrical conduit. The client recently constructed a new manufacturing facility in Greensburg, Pennsylvania, with an investment of approximately $3 million.
Process
The analysis commenced with a thorough on-site inspection on December 12, 2023, coupled with a detailed review of the facility’s blueprints. Given that the building was placed in service in a prior tax year, our Fixed Assets team’s approach included a crucial 481(a) calculation to rectify improper depreciation methods. This additional step allowed for correction without the need to amend previous tax returns, with effects recognized in the current tax year. As part of the comprehensive service, we also provided a draft Form 3115 and accompanying attachment.
Study Results
The cost segregation study was completed on January 16, 2024, delivering exceptional outcomes for the client within a four-week turnaround time. Our team successfully reclassified 25% of the facility’s assets from 39-year property into 5-, 7-, and 15-year property categories. These reclassified assets, all eligible for bonus depreciation, totaled approximately $750,000 of the overall project cost.
The study’s findings significantly exceeded initial projections, increasing the client’s first-year cash flow by an additional $100,000 above expectations. Notably, the client’s return on investment was an impressive 33 to 1 ratio. The first-year increased cash flow was $186,202, and the present value of increased cash flow was $180,008.
-
$180,008
Net Present Value
Contact Us
Help your clients save more with expert guidance from McGuire Sponsel.
Schedule a conversation today and see how we assist CPAs.
Additional Resources
-
Fixed Asset ServicesJanuary 13, 2026
Metal Sprocket Manufacturing Facility Cost Segregation Study
by Dave McGuireLearn how a $3M manufacturing facility achieved a 17:1 ROI through a cost segregation study, accelerating depreciation and boosting first-year...
-
Fixed Asset ServicesJanuary 13, 2026
Minnesota Apartment Complex Cost Segregation Study
by Dave McGuireLearn how McGuire Sponsel helped a CPA firm maximize tax savings through a cost segregation study for a renovated apartment...
-
Fixed Asset ServicesJune 22, 2025
Specialized Boat Manufacturing Facility Cost Segregation Study
by Dave McGuireMcGuire Sponsel was contacted by a CPA firm to conduct a cost segregation study for a specialized boat manufacturing facility...
-
Fixed Asset ServicesMay 15, 2025
Texas Food Manufacturing Facility Cost Segregation Study
by Dave McGuireMcGuire Sponsel was contacted by a CPA firm to conduct a cost segregation study for a two-phase construction project for...